So I have two problems.
1. The previous owner of the empennage kit marked on the empennage that the right HS-404 rib needed to be replaced. I wanted to assemble it to see exactly where the problem was and determine if it is fixable. I think I COULD fix it, but its probably better if I simply replace the part. There is a space of about 1/8 inch between the flange of the HS-404 and the front spar. My thought is, that it could probably be reshaped to work since this is not a part that should undergo large structural load... but probably better and easier to just replace the part.

2.